What does the Auto-set to schedule start date mean?
Does it set the start date when you Reschedule Backwards?

Hi,

Thanks for reaching out. If the Work Start Date differs from the Scheduled Start Date, and you click that checkbox, the Work Start Date will change to match the Scheduled Start Date.

Let us know if you need further help on this.

Enjoy your day!
Cetec ERP Support

@Eduff
This is CETECS reply to this Question