Glenda and Jeannie,
Yes, the AP Details report will deprecate but the AP Summary report, with Expand all Details box checked, will still display all the details for all Vendors, or with filter set to any one Vendor. In running both AP reports through 2026-03-10, they both agree in displaying Debit Memo 8, but on 2026-03-11 they differ by the now Open Debit Memo 8 only. We advise using the AP Summary going forward but certainly save the AP Details report as well for documentation regarding this one particular issue in March 2026 and perhaps for June & July month ends as well, with the issue fully resolving as of 2026-08-31. Further details as to the path forward below.
The reason why the two aging reports differ in displaying the Debit Memo 8 is due to this activity on two different AP Payments paying Voucher 794 and including Debit Memo 8:
AP aging report apparently is affected by Debit Memo 8 remaining affected (though is status Open) in the resulting ledger impact regarding the many Reversal action dates, for which there are dates in July 2026 and August 2026 that cause the Make and Cancel entries to not line up with the original entries in March 2026, some of the user make/cancel/make/cancel activity still occurring during the time CETEC support was trying to resolve the issue:
The ledger activity date conflicts that were created are due to multiple, repetitive user action errors, not CETEC system error. The ledger activity date conflicts do fully resolve as of 2026-08-31, and engineers have made the Debit Memo 8 & Voucher 794 open and available to create new AP Payment with both included on an expected March 31, 2026 posting date. The stray Cancel ledger entries on dates in July and August 2026 have been effectively rendered inaccessible to correct by ongoing user action activity, and so must resolve with time as of 2026-08-31.
If the new AP Pmt to pay Voucher 794/DR Memo 8 is to have a date other than March 2026, then a small manual ledger entry at month end for March, adjusting for the Debit Memo amount through April, May, June and July 2026 may be needed to adjust the ledger to agree with the AP aging report as to the amount of 38.75 re: Debit Memo 8. It should be made reversing (with checkbox and date in manual ledger entry edit screen) on 1st of August 2026 when all ledger conflicts as a result of the many mis-dated Cancel AP Pmt entries then fully resolve.
We repeat here earlier recommendation that users refrain from using the Reverse Entry & Clear Entry buttons in the ledger edit screens to avoid similar situation in the future, unless users are specifically instructed to do so by CETEC Support to resolve an issue. Certainly let us know in this forum ticket email thread if the issues do not fully resolve as indicated, either with the added AP Payment in March 2026 or when the ledger conflicts fully resolve at end of August 2026.
Best,
CETEC ERP Customer Support