Does adding a labor plan with a Incoming Receiving and Inspection lead time of 10 days add 10 days to the material need date for an item that needs purchased?
For example,
If an assembly has a BOM of 10 parts and the lead time is 100 days and we have a labor with a Incoming Receiving and Inspection lead time of 10 days would the need by date increase to 110 days?