We weld trailer frames (roughly 8 per day) and send them out to zinc coating (the combo, when returned is an inventory sub assembly). We send the trailers to zinc in batches from 2 to 4 at a time (all different Cetec work orders, because they’re highly configurable). Our zinc plater will not break out the trailers as they use the total weight of all the delivered trailers to determine the cost of their work order (everything on the delivery trailer). The Cetec outside service PO won’t work for this process and I was wondering if anyone can think of an eloquent non labor intensive method to manage this process.
My thought would be to estimate the zinc cost for each trailer size and create a non-inventory BOM item that is issued to the job. Then cut a blanket PO line of 1 each LOT, ZINC PLATING (different non-inventory item) to transact the daily batch zinc trailer shipments and receipts. Just point both non-inventory items to the same specific outside service sub account.
Does this make sense?
Thanks, -Bill